Lightwell House - Progress

  1. Level 5 drywall is complete.

  2. Kitchen cabinets are in along with countertops.

  3. Interior painting next few days.

  4. Bathroom tile is complete.

  5. Finish trim out starts next week

  6. Concrete retaining wall is in progress.

  1. We have framing complete.

  2. Windows and stacking doors are installed.

  3. Roof is complete.

  4. Rough in plumbing and electric complete.

  5. HVAC rough in next week.

  6. Polished concrete floors will start asap.

  7. Siding will start next week

Alston condos progress

  • Exterior paint + windows complete

  • All rough in trades complete

  • Insulation + sound proofing complete

  • Drywall almost complete

  • Next up: Hardwood flooring, tile and kitchen cabinet install